11 Jun 2014

Smu mba production and operationt management sample paper set four



Question:
The different aspects of value engineering are encapsulated into a sequence of steps known as :     
Response:
Process Plan   
Feedback:
Should have chosen
Job Plan  
Feedback:
Value Plan
Wrong
Engineering plan
Feedback:
Not the right choice - Not related to value engg
Question:
Cost of manufacture of processes can be reduced by        
Response:
Standardizing the processes
 
Feedback:
Should have chosen
Simplifying the processes
 
Feedback:
Both a & b.
Wrong
None of the above
Feedback:
Not the right choice
Question:
Value Analysis looks at the manufacturing activities with a view to make the          
Response:
components simpler
 
Feedback:
processes faster
 
Feedback:
products better
Correct
All the above
Feedback:
right choice - Since huge investments are made on the machines, it is mandatory that every component/part used is made as economically as possible
Unit 14 Mark 1
Question:
The concept of value engineering was developed by         
Response:
Ford
 
Feedback:
Toyota   
Feedback:
Should have chosen
The General Electric Corporations (GEC) 
Wrong
Volkswagen
Feedback:
Not the right choice
Question:
In Value Engineering simplification of processes used to manufacture a product leads to        
Response:
Reduction In labour required
 
Feedback:
Reduction in Inventory
 
Feedback:
Improved quality
Correct
Reduction in cost of manufacturing
Feedback:
right choice - By incorporating Value Engineering, the processes gets simplified, leading to overall reduction in cost of manufacturing.
Question:
The procedure of involving suppliers from the design stage is called       
Response:
pro-sourcing   
Feedback:
out-sourcing
 
Feedback:
post-sourcing
Correct
pre-sourcing
Feedback:
right choice
Unit 14 Mark 2
Question:
VA along with ________ approach, is used to attain a good balance of cost.        
Response:
Should have chosen
DFMA - Design For Manufacturability and Assembly
 
Feedback:
PDCA – Plan Do Check Approach
 
Feedback:
Deming’s
Wrong
Jaran’s Quality Trilogy
Feedback:
Not the right choice - impliment qulaity programs
Question:
The implementation of the Value analysis should take place at the ________.       
Response:
Design stage of product
 
Feedback:
Development stage of product
 
Feedback:
Processing stage of product
Feedback:
Correct
Both a & b
Feedback:
right choice - has to be at both the stages
Question:
Engineering starts at the product concept and design and is carried down the ___________.     
Response:
Process chain  
Feedback:
Product chain
 
Feedback:
Should have chosen
Value chain
Wrong
All the above
Feedback:
Not the right choice

No comments: