Smu mba advanced production planning and control sample paper set four



Unit 12-1 Mark 
1. Expand CPOF
Capacity Planning Operation Facility
Capacity Potential using Output Factor
Correct
Capacity Planning using Overall Factors
Wrong
Capacity Procedure using Overall Floating
Feedback:
Not the right choice: Capacity Procedure using Overall Floating is not the standard expansion.

2. The deliverables are the vital things and it should have mandatory task such as ______________
Timely document
Correct
Quality standard
Wrong
Systematic approach
Feedback:
Not the right choice: Systematic approach is the procedure in deliverables.
Significant timeframe

3. Which among the following is the aspect of maintenance planning?
Communication coordination
Wrong
Preventing malfunctioning
Feedback:
Not the right choice: Preventing malfunctioning is the task in maintenance planning
Effective scheduling
Correct
Reducing the waste

4. Which among the following is the tactics followed in human source planning ?
Wrong
Employing new talented people
Feedback:
Not the right choice: Employing new talented people is the requirement in human resource planning.
Short-term cost savings.
Correct
A sufficient staff
Avoid the costing errors

5. Which among the following is the resource increasing alternatives of capacity planning ?
Correct
Facilitating subcontracting
Increasing capacity Bills.
Produce parts with in a defined range of style.
Wrong
Skilled workers are needed
Feedback:
Not the right choice: Skilled workers are needed for the problem in manual operation, not automatic.

6. Which among the following is the output process of Plan and Define Program of quality planning ?
Prototype control plan
Correct
Products assurance
Wrong
Matrix characteristics
Feedback:
Not the right choice: Matrix characteristics plan is the output process of Process Design and Development of quality planning
Quality planning sign off

7. Which among the following is the procedure for capacity planning ?
Adding shifts.
Correct
Resource Profiles.
Feedback:
Right choice: Resource Profiles. is the procedure for capacity planning
Normal stipulated working hours
Balancing resource
1. Match the following sets:
Match
Correct Answer
User answer
Feedback

Shipping buffer
Its a time offset helps us to meet the customer due date by getting products..
Its a time offset helps us to meet the customer due date by getting products..
correct
Assembly buffer
Its a time offset placed at the levels of the main converging point of production..
Its a material release that depends on time of constraints.
incorrect
Buffer
Its a material release that depends on time of constraints.
Its a material release that is connected virtually, for gating operation.
incorrect
Rope
Its a material release that is connected virtually, for gating operation.
Its a time offset placed at the levels of the main converging point of production..
incorrect

2. Assume that you are a manager of synchronous manufacturing department in an organization. Your department has developed a time phased plan to assign work on the team. Which among the following approach of Synchronous Manufacturing (SM) would you think it essential to address
Wrong
Taking note of the startup inventory level of each item
Feedback:
Not the right choice: Taking note of the startup inventory level of each item is a implementation level of a new system in SM. Not the approach of SM.
Correct
Adjusting each inventory buffer to protect the material flow.
Identify system constraints and determine how to exploit system constraints
Reduce inventories and lead times.

3. State whether the following statements are True or False:
1. The performance of the manufacture system will be poor and the use of time constraints concept (TOC) will be not benefit, if its not follow the production rules of SM .
2. Determination of batch size is important in bottleneck resources.
3. Large batch size are mostly used for non-bottleneck resource.
4. The use of capacity-constrained resource is that preventing resource not to become a bottleneck operation.
Wrong
1T, 2F, 3T , 4T
Feedback:
Not the right choice: Statement 1 is true as the performance of the manufacture system will be poor and the use of time constraints concept (TOC) will be not benefit, if its not follow the production rules of SM . Statement 2 is false determination of batch size is important in SM .Statement 3 is false ,Large batch size are preferable for bottleneck resource. Statement 4 is true, as the use of capacity-constrained resource is that preventing resource not to become a bottleneck operation.
1F, 2T, 3T ,4T
Correct
1T, 2F, 3F ,4T
1T, 2T, 3T ,4T